MISO

MISO 00001
Published On: 05/16/2018

Question: Will you accept an aggregation of distributed generation projects?

Answer: Facilities must qualify as a MISO internal resource and qualified to receive Zonal Resource Credits in or delivered to MISO Local Resource Zone 6 consistent with MISO’s Module E Planning Resource Auction or successor.  A bidder may be able to structure a PPA arrangement for non-conforming assets.

MISO 00002
Published On: 05/25/2018

Question: Does the vendor need to manage the registration and dispatch of demand response load into MISO?

Answer: Generally, Proposals shall take into consideration NIPSCO acting as the MISO Market Participant (responsible for market offers).  However, NIPSCO is willing to consider Proposals where NIPSCO is not acting as the MISO Market Participant to the extent it is beneficial to NIPSCO’s customers. 

To the extent NIPSCO is responsible for registration of the Demand Response asset in MISO, the RFP does require that assets be qualified to receive Zonal Resource Credits in or delivered to MISO Local Resource Zone 6 consistent with MISO’s Module E or successor. Any executed agreement that fails to achieve registration with MISO, regardless or the registering party, will be void.